RRB Group D 2025 · 21 August 2026 · Shift 1
A technician is designing a solar power plant in central India. Understanding the value of the solar constant is necessary for planning the plant’s capacity as:
Think first, then check the answer.
Show the answer and explanation
✓ Correct answer: B. It indicates energy available before atmospheric loss
The solar constant (about 1.36 kW/m²) is the solar energy received per second per square metre at the top of Earth's atmosphere, before any loss by absorption or scattering. It sets the upper limit of energy a solar plant can expect.
📖
Easy notes on this chapterThe Universe, Astrophysics and India's Space Missions
Read the notes🗺️
This topic on the mind mapPhysics › The Universe, Astrophysics and India's Space Missions › The Sun · 🔒 Full subject ₹99
Open the mind map⏱️
Take this whole paperRRB Group D 2025 · 21 August 2026 · Shift 1 · Practice or ⏱️ test mode: real exam time and marks · 📜 PYQ Pass
See the paperMore PYQs from this chapter
- If a spacecraft travels at 30 km/s, how long will it take to cover 1 AU (150 million km)?SSC GD 2026 · 27 April · Shift 2
- An engineer has been asked to monitor changes in the Earth's surface using radar, even through clouds and at night. Which mission suits thi…SSC GD 2026 · 28 April · Shift 3
- Which Indian rocket is called the 'Fat Boy'?SSC GD 2026 · 28 April · Shift 3
- Orion is a ______.SSC GD 2026 · 29 April · Shift 1
- Which telescope provided the first direct image of a black hole?SSC GD 2026 · 29 April · Shift 2